Marietta would get $78.2 million of the $1.15 billion Cobb SPLOST on the Nov. 3 ballot: $13.2 million for repaving, a rebuilt Fire Station 55 and new parks.

Marietta would receive $78.2 million over six years if Cobb County voters renew the 1% special purpose local option sales tax on Nov. 3. The biggest single items on the city’s list are $13.2 million for street resurfacing and $9.35 million to rebuild or remodel Fire Station 55.

The tax is known as SPLOST. The referendum is on the ballot countywide, including inside the city.

What is on the ballot

The Cobb County Board of Commissioners approved the 2028 SPLOST project list on April 28, according to the county’s 2028 SPLOST renewal page. The county’s August overview brochure sets out the numbers:

  • six-year collections of $1.15 billion
  • the current SPLOST expires Dec. 31, 2027
  • the renewal would run from Jan. 1, 2028, to Dec. 31, 2033
  • Cobb’s seven cities would share $355,498,437

The county calls the measure “NOT A TAX INCREASE,” because the renewal would replace the tax that ends in 2027. It says Cobb’s 6% total sales tax would stay tied for the lowest in Georgia. The tax is renewed if more than half of the votes cast are yes.

Marietta’s share

Marietta’s $78,227,427.76 is the second-largest city share, after Mableton’s $97,054,953.54. Smyrna, about seven miles southeast, would get $70,859,757.88 and Kennesaw, about seven miles northwest, $46,771,381.19.

The Marietta City Council approved its list on Feb. 11, 2026, the city’s Transportation Department page says. Every figure below comes from the city’s 2028 SPLOST Tier 1 project list (PDF).

Bar chart of Marietta's proposed 2028 SPLOST spending by group, in millions of dollars over six years: citywide streets, sidewalks and traffic 33.18, police and fire 25.62, parks and City Hall 9.29, five street corridors 5.44, ward projects 3.5, sanitation trucks 1.2.
Chart by Marietta Today. Source: City of Marietta, 2028 SPLOST Tier 1 project list.
Share this chartFacebookWhatsAppX

Streets, sidewalks and traffic: $33.2 million

Project Amount
Citywide street resurfacing $13,200,000
Citywide sidewalk and trail construction $6,250,000
Citywide streets and drainage improvements $5,000,000
Citywide traffic management system (ATMS) $3,500,000
Program administration $2,681,108.75
Gateway improvements $1,500,000
Bridge rehabilitation $500,000
Signage upgrades $275,000
Street marking upgrades $275,000

Police and fire: $25.6 million

Project Amount
Rebuild or remodel Fire Station 55 $9,350,000
Police vehicle replacement $4,980,000
Police training center interior buildout $1,675,000
Fire emergency radios $1,650,000
Police emergency radios $1,650,000
Fire heavy-duty service truck $1,440,000
Fire engine replacement $1,200,000
Fire training facilities and equipment $1,100,000
Police training facilities and equipment $1,100,000
Remodel Fire Station 52 $1,075,000
Police weapons and equipment $396,450

Parks and City Hall: $9.3 million

  • $3.54 million to replace the turf at the Franklin Gateway Sports Complex
  • $2 million for City Hall renovations, including ADA upgrades
  • $2 million for park improvements citywide
  • $1.75 million for a new park in Ward 7

Five street corridors: $5.4 million

  • Cherokee Street, Chicopee Drive to Tower Road: $2,925,000
  • Lawrence Street, Cole Street to Fairground Street: $1,554,869.01
  • North Marietta Parkway streetscape, Church Street to Fairground Street: $500,000
  • Atlanta Street streetscape, South Marietta Parkway to the Square: $360,000
  • Whitlock Avenue, North Marietta Parkway to John Ward Road: $100,000

Ward projects and trash trucks: $4.7 million

Each of the city’s seven wards would get $500,000 for sidewalks, streets and traffic calming, a total of $3.5 million. Sanitation truck replacement accounts for $1.2 million.

The second-tier list

The county’s booklet also prints a longer Tier 2 list for Marietta, beyond the $78.2 million. It does not say when or whether those projects would be paid for. The largest include:

  • Merritt Road Park development: $7.8 million
  • a city training and classroom building: $6 million
  • Custer Park sports and fitness center expansion: $5.55 million
  • more parking at the Franklin Gateway Sports Complex: $5.4 million
  • silent railroad crossings downtown, a quiet zone: $3 million

What the county would build

The county’s own $794.5 million share would pay for a new State Court building, a new infirmary at the Cobb County jail, two new fire stations, renovated police precincts and radio upgrades, its brochure says. It also lists a replacement for the Central Aquatic Center, an expanded Tim D. Lee Senior Center and a new 20,000-square-foot East Cobb library.

The full county list is in the 2028 SPLOST booklet (PDF).

What it means for you

  • To ask questions in person, the county’s last education session is 5:30 p.m. Tuesday, Oct. 27, on the second floor of the David Hankerson Building, 100 Cherokee St. Questions can also go to splostcomments@cobbcounty.gov.
  • To vote early, early voting runs through Friday, Oct. 30. Mail ballot applications close Friday, Oct. 23. Sites and hours are on our Cobb County voting guide.
  • On Election Day, Tuesday, Nov. 3, polls are open 7 a.m. to 7 p.m.
  • For road work already underway with earlier SPLOST money, see our road construction and closures page.